A construction lien is a claim against your property by someone who improved it and wasn't paid. Florida's rules are in Part I of Chapter 713. The warning that has to appear in your contract puts it plainly: if your contractor fails to pay subcontractors or suppliers, "those people who are owed money may look to your property for payment, even if you have already paid your contractor in full" (s. 713.015).
Small jobs are mostly exempt
Any improvement where the direct contract price is $2,500 or less is exempt from the rest of Part I except s. 713.05, which covers lienors in privity with the owner (s. 713.02(5)). Your own contractor can still claim a lien on a small job; subs and suppliers generally can't.
The documents, in order
| Step | Who | Deadline | Statute |
|---|---|---|---|
| Lien law warning in your contract (homes up to 4 units, over $2,500) | Contractor | At signing | s. 713.015 |
| Notice of Commencement recorded and posted | You (owner) | Before work starts; before the first inspection | s. 713.13 |
| Notice to Owner | Subs and suppliers you didn't hire directly | Before, or within 45 days after, they start furnishing; always before your final payment | s. 713.06(2)(a) |
| Partial releases with progress payments | Lienors you pay | With each payment | s. 713.06(3)(c) |
| Contractor's final payment affidavit | Your contractor | When final payment comes due; at least 5 days before it sues to enforce a lien | s. 713.06(3)(d) |
| Claim of lien recorded with the clerk | Any unpaid lienor | Within 90 days after its final furnishing | s. 713.08(5) |
| Lawsuit to enforce | Lienor | Within 1 year of recording, or 60 days after you serve a Notice of Contest | s. 713.22 |
The Notice of Commencement has its own page: Florida Notice of Commencement.
The Notice to Owner
Every lienor who isn't in a direct contract with you, other than laborers, must serve you a Notice to Owner as a prerequisite to a lien. The deadline is "before commencing, or not later than 45 days after commencing, to furnish his or her labor, services, or materials, but, in any event, before the date of the owner's disbursement of the final payment after the contractor has furnished the affidavit" (s. 713.06(2)(a)). Failing to serve it on time "is a complete defense to enforcement of a lien by any person."
The statutory form opens with this warning:
WARNING! FLORIDA'S CONSTRUCTION LIEN LAW ALLOWS SOME UNPAID CONTRACTORS, SUBCONTRACTORS, AND MATERIAL SUPPLIERS TO FILE LIENS AGAINST YOUR PROPERTY EVEN IF YOU HAVE MADE PAYMENT IN FULL. ... TO AVOID A LIEN AND PAYING TWICE, YOU MUST OBTAIN A WRITTEN RELEASE FROM US EVERY TIME YOU PAY YOUR CONTRACTOR.
A Notice to Owner isn't a lien and doesn't cloud your title. Keep every one you receive in a folder with the contract. Each one is a name you'll need a release from.
Paying safely
Progress payments
When a progress payment comes due, you're supposed to pay each lienor who has given you notice the amount then due to it, and those lienors sign partial releases for what they receive (s. 713.06(3)(c)). You may require the contractor to give you an affidavit listing unpaid bills before each payment. You owe nothing to a lienor, other than laborers, who hadn't served a Notice to Owner when you paid.
The final payment affidavit
When final payment becomes due, the contractor must give you a sworn Contractor's Final Payment Affidavit stating that all lienors who timely served a Notice to Owner have been paid in full, or listing each unpaid one and the amount owed (s. 713.06(3)(d)1.). The contractor has no lien or right of action against you while in default for not giving it. If the affidavit lists unpaid bills, you may pay them directly after giving the contractor at least 10 days' written notice and deduct those amounts from what you owe (s. 713.06(3)(d)2.).
DBPR's lien law brochure (PDF) adds practical advice: ask the contractor, by certified or registered mail, for a list of every sub and supplier on your job, get partial releases with each payment, and get final releases from the unpaid parties on the affidavit before the last check.
If a lien is recorded
- Check the 90 days. Compare the recording date with the claimant's last day of work or delivery (s. 713.08(5)).
- Check the Notice to Owner. A sub or supplier who didn't timely serve one has no enforceable lien (s. 713.06(2)(a)).
- Check the license. No lien exists in favor of an unlicensed contractor, subcontractor or sub-subcontractor (s. 713.02(7); s. 489.128).
- Consider a Notice of Contest of Lien. Recording one with the clerk limits the lienor to 60 days from service to sue, or the lien is "extinguished automatically" (s. 713.22(2)).
- Ask a court. Any interested party can file a complaint asking the court to order the lienor to show cause within 20 days why the lien shouldn't be enforced or canceled (s. 713.21(4)).
If the lien exists because your contractor took your money and didn't pay the claimant, that may also be a disciplinary violation. Failing to remove such a lien within 75 days counts as financial mismanagement under s. 489.129(1)(g), which is one of the grounds for a recovery fund claim.
Misapplied money is a crime
Anyone who receives payment for improving real property must apply it to amounts already due for labor, services and materials on that job, except for good-faith disputes and contract terms (s. 713.345(1)(a)). Knowingly and intentionally failing to do so is misapplication of construction funds, a felony at every amount: third degree under $1,000, second degree from $1,000 to under $100,000, and first degree at $100,000 or more (s. 713.345(1)(b)).
Lien law is technical. DBPR notes that it and the CILB don't regulate the lien law and suggests an attorney experienced in it (CILB FAQs).
Related pages
Sources
- Chapter 713, Part I, F.S. (2026 Florida Statutes), including ss. 713.015, 713.02, 713.06, 713.08, 713.13, 713.21, 713.22, 713.345
- s. 489.128 and 489.129, F.S.
- DBPR brochure: Florida's Construction Lien Law (PDF)
Frequently Asked Questions
Can a subcontractor put a lien on my house if I paid my contractor in Florida?
Yes. The statutory Notice to Owner warns that Florida's lien law allows some unpaid contractors, subcontractors and material suppliers to file liens 'even if you have made payment in full' (s. 713.06(2)(c), F.S.). That's why you should get a written release from each party that served you a Notice to Owner every time you pay.
How long does a contractor have to file a lien in Florida?
A claim of lien may be recorded during the work or afterward, but no later than 90 days after the lienor's final furnishing of labor, services or materials (s. 713.08(5), F.S.).
How long does a construction lien last in Florida?
One year after the claim of lien is recorded, unless an action to enforce it is filed in that time (s. 713.22(1), F.S.). You can shorten that to 60 days by recording a Notice of Contest of Lien (s. 713.22(2)).
Can an unlicensed contractor put a lien on my house in Florida?
No lien exists in favor of a contractor, subcontractor or sub-subcontractor who is unlicensed under s. 489.128 or s. 489.532 (s. 713.02(7), F.S.).