Florida has a single statewide building code, the Florida Building Code, enforced by local building departments. Under s. 553.79(1)(a), "it shall be unlawful for any person, firm, corporation, or governmental entity to construct, erect, alter, modify, repair, or demolish any building within this state without first obtaining a permit" from the appropriate enforcing agency, unless the law provides otherwise. The Florida Building Commission lists the Florida Building Code, 8th Edition (2023), effective December 31, 2023, as the current code (floridabuilding.org).

Your county or city building department issues the permit, inspects the work, and decides what your particular project needs. Call it before you sign a contract.

The 2026 exemption for work under $7,500

A law that took effect July 1, 2026 (ch. 2026-63, Laws of Fla.) added a permit exemption for small single-family jobs. A local government that issues building permits "shall exempt an owner of a single-family dwelling or the owner's contractor from the requirement to obtain a building permit to perform any work valued at less than $7,500 on the owner's property" (s. 553.79(1)(g)).

It does not apply to:

  • Work on a property partly or entirely in a flood hazard area as defined by the Florida Building Code
  • Any electrical, plumbing, structural, mechanical or gas work on a property with a single-family dwelling

To use it, you or your contractor must submit a written request to the local enforcement agency with a copy of the contract or other documents showing the nature and value of the work. You can't split one project into several to stay under the limit, and the local government "has no legal duty" to you for exempted work (s. 553.79(1)(g)3.-4.).

The exemption is about permits only. A job under $7,500 can still require a licensed contractor; see work that doesn't need a state license.

Temporary flood barriers

The same law requires local governments to exempt temporary residential hurricane and flood protection walls or barriers that are non-habitable and non-load-bearing, installed on a single-family, two-family or townhouse property by a contractor licensed under Part I of Chapter 489, and compliant with local zoning, drainage, easement and setback rules. It doesn't apply in flood hazard areas, and a written request is required (s. 553.79(1)(h)).

Contractors must have a permit in place

A contractor may not "commence or perform work for which a building permit is required ... without such building permit being in effect" (s. 489.127(1)(h)). Proceeding on a job without the applicable local permits and inspections, unless otherwise provided by law, is grounds for discipline (s. 489.129(1)(o)). A contractor who suggests skipping the permit is offering to break two statutes.

A licensed contractor also may not pull a permit for work it hasn't contracted to do (s. 489.127(4)(c)), and it must put its license number on each permit application (s. 489.119(5)(a)).

Review deadlines

Section 553.792(1)(a) sets deadlines for a local government to approve, approve with conditions, or deny a complete and sufficient application, when you use the local government's plans reviewer:

Permit Deadline
Existing single-family home, work under $15,000: structural, accessory structure, alarm, electrical, gas, irrigation, landscaping, mechanical, plumbing or roofing 5 business days
Residential units and related trade permits, structure under 7,500 sq ft 30 business days
Same, structure 7,500 sq ft or more 60 business days

Within 5 business days after you apply, the local government must tell you in writing what's missing. If it doesn't, the application is deemed complete (s. 553.792(1)(c)). You can waive the deadlines in writing, but the local government may not require a waiver before it reviews your application.

Permit expiration

A building permit for a single-family dwelling "expires 1 year after the issuance of the permit or on the effective date of the next edition of the Florida Building Code, whichever is later," and the local government may extend it (s. 553.79(1)(c)). The local government may email or mail you and your contractor an expiration notice at least 30 days ahead.

Other rules that ride along with the permit

  • Notice of Commencement. For direct contracts over $5,000, the permit office must receive a copy before the first inspection (s. 713.135(1)(e)). See the Notice of Commencement page.
  • Owner-builder permits. If you pull the permit yourself, you sign the statutory disclosure statement; see owner-builder rules.
  • Private providers. You can hire a licensed private provider for plan review or inspections and get a reduced permit fee; see private provider inspections.
  • Electronic filing. Local building departments must accept permit applications and inspection requests electronically (s. 553.79(1)(b) and (d)).
  • Denials must cite the code. If a permit is denied or revoked for code noncompliance, the agency must identify the specific plan features and code sections involved (s. 553.79(1)(a)).

Related pages

Sources

Frequently Asked Questions

What work is exempt from a building permit in Florida?

Since July 1, 2026, a local government must exempt a single-family owner or the owner's contractor from a permit for work valued under $7,500 on the owner's property. The exemption doesn't apply in flood hazard areas or to any electrical, plumbing, structural, mechanical or gas work, and you must submit a written request with the contract or other proof of the work's nature and value (s. 553.79(1)(g), F.S.).

How long does a Florida building permit last?

A building permit issued by a local government for a single-family dwelling expires one year after it is issued or on the effective date of the next edition of the Florida Building Code, whichever is later. The local government may extend it (s. 553.79(1)(c), F.S.).

How fast must a Florida building department approve a permit?

For an existing single-family home, certain permits for work valued under $15,000, including roofing, electrical, plumbing and mechanical, must be approved, approved with conditions or denied within 5 business days after a complete application. Residential permits for structures under 7,500 square feet have 30 business days (s. 553.792(1)(a), F.S.).

Which edition of the Florida Building Code is in effect?

The Florida Building Commission's website states that the Florida Building Code, 8th Edition (2023), took effect December 31, 2023.